After the framer did a great job on our house, the rough in started and we can see mayor transformation "in" the house.
Electrical wiring started after the plumers have done the basement and upper floor's water and waste pipes rough-ins.
The HVCA came after and last the insulation.
Due to some building code changes, our house got hold at the pre-wall inspection: the inspection failed.
Sterling Homes did not provide the actualized blue-print design plan on a high wall that their engeenering has changed but did not sumit it to city of Calgary, therefore, when the inspector came the actual construction differed from his construction specs.
This and the garage's walls that are supporting the upper floor's rooms, excceded 3 meters and the material that we used are 2x4 insteate of 2x6.
and some other minor taht are conditionally acceptable.
All this had hold the construction to advance for one week+,